Update: Electric Service Restored 3:35pm
/FPB Electric crews have completed repairs and service should be restored to the impacted area of Crestwood. Thank you for your patience during the service issue.
FPB Electric crews have completed repairs and service should be restored to the impacted area of Crestwood. Thank you for your patience during the service issue.
FPB Electric customers in Crestwood Subdivision may be experiencing a service interruption. Crews are aware of the issue and working on restoring service. Thank you for patience during this electric service issue.
FPB Cable crews will conduct system maintenance on Monday, August 22.
The maintenance window is scheduled for 1:00am until 6:00am Monday morning and will have a brief impact on all FPB Cable channels. Crews expect the entire maintenance window to be short in duration and hope to limit the service disruption to a few minutes per customer/per network.
We apologize for any inconvenience during this necessary maintenance.
As a result, the Frankfort Plant Board (FPB) as well as other Kentucky municipals gave notice to terminate their contracts with Kentucky Utilities (KU) in April 2014. The termination of the existing contract requires FPB and the other municipals to acquire new electric service and begin taking that service as follows: June 1, 2015 for the Benham Power Board; May 1, 2017 for the City of Paris; and May 1, 2019 for the Frankfort Plant Board and the Cities of Barbourville, Bardwell, Berea, Corbin, Falmouth, Madisonville, and Providence, Kentucky.
On June 16, 2015, the Board approved the Interlocal Cooperation Resolution and Agreement which authorized and established the Kentucky Municipal Energy Agency (KyMEA). Also at that meeting the Board appointed and approved its representative and an alternate to the KyMEA Board of Directors. This action was taken by FPB and eight other municipals in order to realize the benefits from economies of scale in planning, purchasing, selling and operating power supply resources. On November 19, 2015 the Board also conducted a televised, public forum to discuss and inform our community about KyMEA and the progress being made on a new power supply.
Since that time the KyMEA Board and its consultant team have continuously worked to acquire a new energy supply. A number of major elements must be addressed before any new service can begin. Some (but not all) of those elements are identifying and procuring power supply resources, securing transmission service and establishing power delivery contracts between the municipals and KyMEA.
By way of the Kentucky model procurement code, KyMEA has identified key portions of the power supply resources that will be used during the first few years of service. While portions of the power supply portfolio for KyMEA have been established, there are still additional resources and contracts that will need to be worked out in the coming months and years. This resource planning and procurement will be a continuous process for KyMEA as contracts of varying terms and resource types, evolve and expire.
Applications, studies, system modeling and identification of possible upgrades that may be needed are currently underway to establish transmission service to each of the KyMEA members.
In an effort to establish power delivery contracts between the municipals and KyMEA, the KyMEA Board has approved and is proposing the all-requirements contract for FPB’s consideration. Staff and our consulting team presented the details of the proposed all-requirements contract between FPB and KyMEA at the regular July 19, 2016 Plant Board meeting. Staff and the consultant group firmly believe it is in our community’s best interest to approve the resolution and contract to become an all-requirements partner in KyMEA.
The Frankfort Plant board approved the all-requirements contract at the Aug 17 regular board meeting. The presentation from the Board meeting is provided here.
Crews have made repairs and power should be restored to the impacted area. Thank you for your patience during this service issue.
FPB Electric crews are currently investigating a service interruption throughout parts of the service area. Areas impacted include: parts of Tanglewood, Hay Ave., Capital Heights, Altamont, and Second St. We appreciate your patience while crews work restore power.
FPB Electric customers in parts of downtown may be experiencing a service interruption. Impacted areas include: East Second, East Third, East Fourth, Murray St., Logan St. and Fannin Court. Crews are aware of the issue and working on a resolution. Thank you for patience during this service issue.
Please note, not every customer will be affected entirely during these necessary maintenance windows. There will be no interruption to FPB internet, telephone, or security services.
FPB apologizes to its customers for the inconvenience.
Thank you for your patience during this necessary maintenance.
FPB Cable crews will conduct planned maintenance beginning August 1, 2016. FPB Cable television customers may experience multiple service interruptions from 1:00am-5:00am, Monday – Friday (August 1-5).
Please note, not every customer will be affected entirely during these necessary maintenance windows. There will be no interruption to FPB internet, telephone, or security services.
FPB apologizes to its customers for the inconvenience.
Thank you for your patience during this necessary maintenance.
FPB Electric crews have restored electric service to the majority of the east side of Frankfort. Thank you for your patience during this storm related outage.